Side Keels

Posted on

side keels 7 scaled

The side keels have now been welded up and are in the workshop, for prep work then epoxy coating.

We will be grinding the surface using 4.5-inch grinders and a standard dry stone, the surface will be cleaned with biosolv, once we are happy with the surface we will paint on with a scrubbing action 1 coat of low vis epoxy with a mixture of 50% fast hardener and 50% medium hardener. this will give us a quick jell time without being too quick to work

 

side keels 7
Bilge Keels for the schooner
side keels 6
Keels of Schooner ready to be lifted
side keels 2
Lifting bilge keels ready to move into workshop